|
Projects
| Integrated
Solutions are a credible and experienced company. Below is a
list of some of the projects Integrated Solutions have undertaken.
These examples clearly demonstrate the quality which our service
provides. |
To
view more information on the following project examples, please
select from the drop down menu to the right.
- Environmental
Health Check Report
- Water
- (1.Monitoring/measurement of various determinands
released into water.)
(2.Help was provided to a company to identify a non-return
to sewer.)
- Air
- (Reduction in the release of gas to atmosphere.)
- Systems
- (1.The company expressed a wish to compile an
integrated management system which met all the requirements
of the following three standards: BS EN ISO9001:2000, BS
EN ISO 14001 and BS 18001.
(2.
gaining BS EN ISO14001 certification)
- Land
- (Possible pollution to a beck).
|
|
Water
1
Background
A
company is involved in the manufacture of cellulose acetate fibre
and is registered under the EPA Part A s4.2 The manufacture and
use of Organic Chemicals.
Services
provided
We
have been working with the company for over six years aiding in
the monitoring/ measurement of various determinands released into
water and which are an integral part of the consent to operate the
process. We have been asked to monitor Biological Oxygen Demand,
Chemical Oxygen Demand, Flow (in various channels), methanol, ethyl
acetate, methylene chloride and benzene, metals in water discharges
and in soil/effluent pit samples, total phosphorus in effluent samples
and dissolved solids. The aim of the ongoing work is to confirm
compliance with the conditions attached in the process authorisation.
The
secondary aim is to aid in improving the balance of emission to
any of air, land, or water by having knowledge of baseline chemical
mass balances. In some cases conditions are deliberately set up
to deliver worst case results. By using these techniques, we can
not only achieve compliance, but work towards best practice.
We
have taken a total of 1750 samples to date and spent over 350 days
on this project; regular weekly visits are made to site to complete
the routine sampling and to undertake any special projects. We are
in some cases required to work under permit to work conditions.
Site access can only be gained after undertaking awareness training
and passing a test to an approved standard to verify knowledge;
updates must be gained on an annual basis in order to retain permission
to work in all areas of the site.
Top of Page
Water
2
Background
Help
was provided to a company to identify a non-return to sewer. The
company was being charged as though all the mains water metered
in was sent back to the effluent drains system/sewer, however it
was proven that 66% was lost through evaporation in the cooling
tower system. The company saved £6,000 on the invoicing of
water per annum as a result.
Services
Provided
Monitoring
of all effluent drains and foul sewers was undertaken over an agreed
time period to establish the quantities by volume of effluent/sewerage
leaving the factory system. Where the pathway for the effluent was
not totally clear (100%) tracing dyes were used to ensure the exact
routing was known particularly between effluent and foul sewers.
It
was established that the quantities of effluent/sewerage leaving
the factory did not coincide with those metered in; there was a
major difference that required further investigation.
It
was proven, to the satisfaction of North West Water, that water
was being lost in the cooling towers through evaporation, thus the
water bill could be substantially reduced (see above). A North West
Water Authority representative visited the site to see the set
up and to verify the figures provided by our monitoring. Aid
was provided to the company in completing the relevant forms and
paperwork.
Top of Page
Air
Background
Etching
of tungsten wire wound around a molybdenum mandrel was undertaken
using
a mixture of strong acids to incorporate nitric acid. As the metal
was etched ( dissolved) gases
were given off and taken via a ventilation system to a scrubber
that cleaned up the resultant gas stream prior to release to atmosphere.
The mandatory limit for release to atmosphere at that time was 1500
p.p.m. of Nox (nitrogen oxide mixed gases).
Services
Provided
A
study of the performance of the scrubber unit was undertaken to
evaluate the following parameters:
i)
Optimisation of the concentration of the scrubbing agent;
ii) Optimisation of the type of scrubbing agent utilised;
iii) Efficiency of the scrubbing column.
Prior
to the start of the practical work activity full research was undertaken
so as to gain knowledge of what had already been researched in this
technology area.
The
outcome of the work was to achieve a reduction in the release of
gas to atmosphere to well below previously achieved performance
( nominal was about 1000 p.p.m.). The new resulting normal level
of gas release was now less than 200 p.p.m.. This release concentration
to atmosphere was below expectations and had never been achieved
previously on a continual basis.
Top of Page
Systems
1.
Background
A
company largely working in the nuclear industry had achieved BS
EN ISO9001:1994 certification, had some environmental management
systems in place, although they were not totally implemented and
some evidence of the performance of risk assessments for a variety
of work operations. The company became aware that this methodology
left a number of significant gaps in its overall control systems,
particularly in the light of the proposed changes to ISO9000 series
on quality. The company expressed a wish to compile an integrated
management system which met all the requirements of the following
three standards: BS EN ISO9001:2000, BS EN ISO 14001 and BS 18001.
Services Provided
Initial
effort concentrated on the definition of the key activities of the
company (these are the processes as defined in the standard). The
decision reached was that there were three main activities a) Project
Management, b) Assurance Services (to be the QSHEW - quality, safety,
health, environment and welfare), c) other ancillary activities
and support functions such as administration. A flow chart was constructed
of all key links, activities and communications. This flow chart
facilitated choices as to how the procedures were to be placed into
groups. Each procedure was to be accompanied by an appropriate flow
chart to facilitate a change over to the new format at some future
date (the procedures themselves would become defunct in time as
staff became used to using new format material.
Over
a period of eighteen months the manual was rewritten, formatted
against the clauses of ISO14001, the procedures were rewritten and
a project plan generated for the company head office.
All
external audits have successfully concluded that the system meets
the requirements of all three standards.
Top of Page
Systems
2
Background
A
company supplying polyvinyl chloride products to the automotive
market requested that we aid their organisation to gain BS EN ISO14001
certification due to supply chain pressure within that industry.
Services
Provided
Help
was provided to the company to develop its register of effects,
to score each effect under varying conditions (incident and emergency)
and to place each one in traceable format in the system.
This
part of the system development was regarded as the rate determining
step since the organisation had a number of differing and
complex processes on site (as examples printing, compounding and
spreading).
Other
key aspects of the system such as compiling a register of applicable
law, an operations manual, a policy statement, identifying objectives
targets and programmes were specifically linked in to the aspects,
as seen fit, particularly those that were termed significant. A
full set of procedures were drawn up to reflect the daily working
practices of the company (this included some documents identified
as work instructions).
The
whole system has been subjected to external assessment and has been
proved to be meeting the requirements of the standard.
Ongoing
help has been provided with regard to internal auditor training
and awareness, as well as the upkeep of the legal register.
Top of Page
Land
Background
A
waste compound that was used to store a wide range of potentially
toxic chemicals was situated close to a controlled water (a beck).
Although the compound was fully enclosed (bunded) it was possible
during periods of heavy rain for an interceptor to overflow and
causing possible pollution to the beck. The pollution could cause
harm that would be an offence under s85 of the Environmental Protection
Act 1990, if proven. It was also possible for adjoining land to
be contaminated.
Water
that collected in the compound could only be disposed of as special
waste, since it was contaminated with potentially harmful chemicals.
A holding tank was in place to allow a waste management contractor
to collect this waste water on a regular basis and dispose of it
in an approved manner. The annual management cost of the disposal
of the waste water was about £12,000 per annum.
Services
Provided
Advice
was given to the company on ways in which to reduce the risk of
pollution and at the same time save money. A design was drawn up
to incorporate best practice, for example, secure bunding, secure
flooring to avoid land contamination, incorporation of a roof to
eliminate the need to dispose of waste water and removal of the
site to one well away from the beck. In addition new rules were
drawn up for the improved management of the materials held in the
compound.
Top
of Page
|